![]() ![]() During Phase 1, Plummer will complete 30 percent of total plant designs, preliminary engineering, and other elements. The council chose to begin a phased approach to the design process for the new wastewater treatment plant. “That will save quite a bit in operation and maintenance costs,” Paul explained. The city’s goal is to create a new wastewater treatment plant that could eventually treat 3 million gallons per day, according to City Engineer Kacey Paul. The city’s existing 1.5-million-gallon-per-day treatment plant, located near Johnson Park, previously reached 75 percent capacity three months in a row, resulting in a state requirement to increase plant capacity. The vote came during the council’s meeting Tuesday, April 20. ![]() The city of Marble Falls entered into a $1.1 million contract for design and engineering services with the Austin-based firm Plummer to build a new wastewater treatment plant.